Agricultural Conservation Assistance Program
16-
Agricultural Conservation Assistance Program
The contract holder (farmer) is responsible for pung bids out and ulmately holds the contract with the contractor. Districts are responsible for ensuring that the farmer follows statewide guidance during the procurement process. Ulmately, districts should put processes in place to closely monitor and document compliance.
-
Agricultural Conservation Assistance Program
The approved ACAP Bidding Requirements Document describes bidding requirements in detail. Projects between $10,000 and $250,000 require documented price and/or rate quotes. Projects exceeding $250,000 require sealed bids.
-
Agricultural Conservation Assistance Program
Bidding requirements are triggered based on the amount of the ACAP funding expended toward the project. If mulple funding sources are being used to pay for the project, only the amount of ACAP program funding will be considered to determine the type of procurement method required (should the other funding sources not also be subject to bidding requirements). For example, if a project is expected to be quoted at greater than $250,000, but the amount of ACAP funding for this contract will be less than $250,000, small purchase procedures can be followed, and sealed bids are not required.
-
Agricultural Conservation Assistance Program
The SCC recommends that a minimum of 3 quotes be solicited. A good-faith effort must be made to accept and document quotes. If less than 3 quotes are obtained, contact the SCC for approval.
-
Agricultural Conservation Assistance Program
Under Uniform Guidance, non-Federal enes must comply with the more restricve of the Federal, state, and enty-level requirements. If your county has more restricve requirements, they must be followed.
-
Agricultural Conservation Assistance Program
For projects where ACAP funds exceed $250,000, public advertising is required.
-
Agricultural Conservation Assistance Program
For projects where ACAP funds exceed $250,000, a public bid opening is required.
-
Agricultural Conservation Assistance Program
No, the bids must only be opened publicly and recorded.
-
Agricultural Conservation Assistance Program
Yes, the farmer must accept the lowest responsive and responsible bidder when using the sealed bids procurement method. For other procurement methods, the lowest quote should be accepted unless there is good cause for declining their quote. If the farmer requests to accept a quote that is not the lowest, contact the SCC for approval.
-
Agricultural Conservation Assistance Program
No, but bid, performance, and payment bonds are recommended for projects exceeding $10,000.
-
Agricultural Conservation Assistance Program
No.
-
Agricultural Conservation Assistance Program
No.
-
Agricultural Conservation Assistance Program
Follow the guidelines for the farmer like any other contractor. If the project is less than $250,000, good faith must be made to obtain quotes for the project. If the project exceeds $250,000, a sealed bid process must be followed. The farmer can submit bids for the work; if they are the lowest responsible bidder, they can be awarded the job. It is recommended that the district develop a policy regarding how much farmers can be reimbursed for their labor.
-
Agricultural Conservation Assistance Program
Unlike prevailing wage requirements, bidding is considered per contract, not the enre project's value. If you intend to solicit services compleng a poron of the project or planned pracces, follow the procurement guidelines based on the value of those services. Each resulng award will require that records are kept documenng the procurement methods used and the raonale behind the acon. This type of procurement for services is likely when the farmer acts as the general contractor for the project.
-
Agricultural Conservation Assistance Program
All materials, supplies, equipment, and services required to complete the project are subject to procurement thresholds outlined in the ACAP bidding requirements document. If a farmer intends to be the contractor, procurement thresholds for items such as materials, supplies, equipment rental, etc., may need to be considered. Follow the thresholds in the approved ACAP bidding requirements document to determine if micro-purchase, small purchase, or sealed bids will be required.
-
Agricultural Conservation Assistance Program
It is crical for the farmer to have a well prepared and binding contract with the supplier or contractor to ensure the successful and mely delivery of services. Districts can provide farmers with template contracts for use that should be tailored to each individual project.